Modifying BIA Results
Adjusting the RTO and Business Impact
As an IRM Manager, you may edit the computed indicators and adjust them.
You can enter new values in the following fields:
Adjusted RTO
Adjusted business impact
Entering the RPO (Recovery Point Objective)
The RPO (Recovery Point Objective) indicates the maximum quantity of data it is acceptable to lose (in time units).
Example: time elapsed between the last backup and the moment the incident happened.
Entering the WRT (Work Recovery Time)
The WRT (Work Recovery Time) specifies the maximum of time tolerated to check the system and/or data integrity.
The WRT corresponds to the time the organization is willing to wait to go from a degraded operating mode to a “back to normal” mode.
*When added to the RTO, the WRT allows to obtain the MTD (Maximum Tolerable Downtime). See Viewing the MTD (Maximum Tolerable Downtime).