HOPEX Business Process Analysis > Organizational Charts and Responsibilities > Organizational process and operation responsibilities (RACI)
Organizational process and operation responsibilities (RACI)
HOPEX Business Process Analysis specifies the responsibility level of the various org-units:
on an operation
on an organizational process. The proposed responsibility levels are as follows:
 
Responsibility
Meaning
Responsible
Org-unit responsible for the operation or process
Responsible
Org-unit monitoring progress of the operation or process and taking decisions.
There is only one "Accountable" org-unit for each action.
Responsible/Accountable
Org-unit executing the operation or process, informs on progress and takes decisions.
There is only one "Accountable" org-unit for each action.
Consulted
Org-unit consulted as first priority before an action or decision.
Informed
Must be informed after an action or decision.
*RACI is the acronym of Responsible, Accountable, Consulted, Informed.
Prerequisites to using RACI
One option is used to display the information about RACI.
To activate this option:
1. In the workspace, open the Options window.
2. In the left tree, select Business Process and Architecture Modeling:
3. Select the Managing RACI (BPMN) / Automatic synchronization of RACI by means of participants check boxes.