CV-1 Vision
CV-1 Description
|
Model
|
Description
|
|
CV-1 - Vision
|
Addresses the enterprise concerns associated with the overall vision for transformational endeavors and thus defines the strategic context for a group of capabilities.
|
Purpose of a CV-1
The purpose of a CV-1 is to:
• provide a strategic context for the capabilities described in the Architectural Description.
• provides a high-level scope for the Architectural Description which is more general than the scenario-based scope defined in an OV-1.
• communicate the strategic vision regarding capability development.
Detailed Description of CV-1
The CV-1 defines the strategic context for a group of capabilities described in the Architectural Description by outlining the vision for a capability area over a bounded period of time.
It describes how high-level goals and strategy are to be delivered in capability terms.
A CV-1 may provide the blueprint for a transformational initiative. The CV-1 may be primarily textual descriptions of the global objectives of the transformation or change program that the Enterprise is engaged in. Of key importance is the identification of Goals, together with the desired outcomes and measurable benefits associated with these.

CV-2 provides metrics against each capability which may be used to successfully measure fielded capabilities. For more information, see
CV-2 Description.
The main items dealt with in this model are goals/objectives and the enterprise vision.
CV-1 Hopex Implementation
Goals can be described through the Hopex objectives. The purpose of the CV-1 in Hopex is to create links between goals and capabilities.
Enterprise Vision
From an enterprise or an enterprise stage, you can define enterprise sub-stages. Each enterprise sub-stage is positioned in the main enterprise according to the main enterprise events, in order to define the transformation roadmap for the enterprise underway.
Viewing the enterprise through a Gantt chart
To have a global view of your enterprise:

In the navigation bar, click
Capability Viewpoint > CV-1 Vision.
The transformation schedule is presented in the form of a Gantt chart.
It enables strategists to plan business and IT capabilities in regards to strategic objectives.
Completing information on enterprise stages
To complete information on stages:

Expand the
Structure section.
The enterprise, the enterprise stages and enterprise sub-stages appear in the form of a tree. Buttons are available in a column to manage the strategic elements consistently.
You can add or assign:
• missions
• transformation stages, whether IT or business
• enterprise goals (which are transformation objectives)
• exhibited capabilities
• strategies
Viewing the enterprise through a hierarchy
To view the enterprise through a hierarchy and or/complete it:
1. In the navigation bar, click Capability Viewpoint > CV-1 Vision > Enterprise Vision Hierarchy.
2. Expand the Strategic View folder of your enterprise.
You can view / create:
• desired capabilities
• enterprise stage components