Viewing Exercise Results
Viewing the Results of Tested BCPs
To view results of BCPs tested by an exercise:
1. See Accessing Exercises.
2. In the exercise properties, select the Results page.
For each tested BCP, you can view:
• status
• execution time
• RTO (of the process)
• whether the BCP failed/succeded
Execution time is compared to the RTO:
|
If the execution time is:
|
... the result is:
|
|---|---|
|
- lower than the RTO
|
Operational
|
|
- higher than the RTO
|
Unsatisfactory
|
Depending on the results of each tested BCPs, two percentages are computed:
• Completion rate: percentage of BCPs that have been carried out
• Success rate: percentage of BCPs that have been performed within a period of time lower than the RTO
Viewing the Exercise Dashboard
Global indicators are available in the upper part of the exercise properties (Characteristics page).
Tested plans
Specifies the number of Business Continuity Plans (BCPs) to execute within the framework of an exercise.
Time elapsed
Time elapsed since the beginning of the exercise.
Completion
Percentage of continuity steps that have been completed (for ongoing or closed BCPs)
Result
The result is available when the exercise is in “Closed” status.
Indicates whether the exercise has failed or succeeded.