To create a steering calendar:
1. In HOPEX Windows Front-End click Tools > Explore.
2. Click Create and select the "Steering Calendar" MetaClass.
3. In the wizard that opens, select the Steering Calendar Type:
Action Plan
Control
Key Indicator
Recommendation
4. Connect a Steering Date (which corresponds to the execution frequency of interest to you).
5. Open the steering date properties and select the Scheduling tab.
6. Specify the information required:
start and end date
*It is recommended to use relative dates on the steering date.
start date and hour (defined in UTC format, in the user or server time zone).
*For details on possible configurations, see the section concerning the scheduler in the "Using the Scheduler" section.
7. Select Execute at start date & time if you wish to launch the execution immediately.