Test Plans Follow-Up
HOPEX Compliance enables follow-up of test plans according to different criteria.
Displaying plan follow-up reports
Reports enable test plan execution follow-up.
To access test plan reports:
1. Open the properties of the plan.
2. Select the Plan Reports tab.
Supervision  
This report offers a summary of test plan tests according to different criteria:
Origin:
punctual test
recurring test
follow-up test
board request
Priority
Low
Medium
High
Score:
Good overall level
Can be improved
At risk
Status
In preparation
in progress
Resources allocation  
The diagram displayed in this report enables comparison of:
persons available
persons required
persons assigned
By default, results relate to the current year, but you can display results for a precise period.
Gantt report  
The Gantt report comprises two parts:
A Gantt chart of tests scheduled between selected dates
A Gantt chart of occupation of controllers on tests between selected dates
Expenses 
This report shows all expenses linked to a plan, as well as breakdown by expense category and by controller.
It allows the director to plan future audits.
Closing plans
When all compliance activities have been terminated, the plan can be closed.
The effect of this action is to close all tests in progress or that have not been canceled.