Specifying the Project Milestones
Between the scheduled start and end dates, intermediate milestones can be defined and associated with deliverables.
Within the framework of project progress follow-up, you can define the level of progress for each milestone.
To add a milestone to a project:
1. Click the Projects > Projects navigation menu.
2. In the edit area, click the Projects tab.
3. Display all the projects.
4. Click the project in question to open its properties.
5. In the project properties window, click the Project Milestones page.
6. In the Milestones section, click New.
The window for creating a milestone appears.
7. Specify:
• The local name
• The scheduled date of the milestone
• A comment if required
8. Click OK.