Creating Test Plans
The test plan is prepared by the internal control director.
The plan is generally defined on a period of one year. This plan contains all tests to be executed in the year.
To create a plan:
1. In the navigation bar, select Testing > Test Plans.
2. Click the New button.
The new plan appears.
3. Open the properties of the plan.
4. In the Characteristics tab, modify the Name of the plan.
5. Select the Nature of the plan:
• Audit
• Test
• Compliance
• Mixed
6. Select the Calendar of the plan.
7. Modify the Begin Date and the End Date if necessary.
8. Click Save.
The plan is created.
You can now create tests directly in the plan page.